New Delhi, Apr. 29 (ANI): The Cabinet Committee on Investment (CCI) has cleared several projects in oil, gas block, power, iron ore and coal sectors.
1. Clearance in respect of NELP (New Exploration Licensing Policy) oil and gas blocks for exploration and production activities.
The Cabinet Committee on Investment (CCI) in its meeting held on April 22 cleared 25 NELP blocks for continued exploration of oil and gas, out of 31 blocks where work had been stopped on account of security restrictions imposed by the Ministry of Defence. Thus, the investment of Rs. 14,766 crore already made in these blocks will be put to use and further investment to the extent of Rs. 10, 360 crores will be made in exploration activities in the next three to five years.
In summary, out of total 40 blocks, 31 blocks have been cleared by CCI at its meetings held on March 20 and April 22. Such clearances will not only put to use an investment of Rs. 73,179.26 crores already made, but also will bring in additional investment of about Rs. 13,632 crores in the three to five years in exploration activities.
Further, on discovery of hydrocarbons, huge investment is expected in developing these blocks. Out of 3,32,960 sq. km area covered by these 40 blocks, 2,66,463 sq. km in 31 blocks would now be available for exploration and production activities.
1. Clearance in respect of power sector projects
The Cabinet Committee on Investment in its meeting held on April 22 also reviewed the status of 20 projects. Out of 20 projects, 13 projects involving investment of about Rs 33,000 crores have now been cleared. This includes North Karanpura Thermal Power Project involving an investment of about Rs 15,000 crores cleared by CCI in its meeting held on February 20.
The Committee has also directed that Vishnugad Pipalkoti Hydro Electric Project, Chamoli, Uttrakhand should be awarded within two months, the revised cost estimates of Kotibhel Hydo Electric Project, Tehri Garhwal, Uttrakhand and Pakul Dul Hydro Electric project, Doda, Jammu and Kashmir should be expedited and the work should be awarded within four to five months.
The Committee also directed that environmental clearance in respect of Feroze Gandhi Unchahar Stage IV, Raebareli, UP be issued within a week.
3. Clearance in respect of Gua iron ore mines in Jharkhand for increase in crude steel capacity of Steel Authority of India Limited (SAIL)
Steel Authority of India Limited (SAIL) had applied for forest clearance for an area of 635.986 ha. This will enable increasing the iron ore production from these mines from 2.4 million tonne per annum to 10 million tonne per annum through an investment of Rs 3000 crores along with installation of beneficiation plant and a pallet plant. This is required for increase in the crude steel capacity of eastern sector steel plants by 5.44 million tonne per annum at an estimated cost of Rs 43,000 crores out of which an investment of Rs 33,000 crores has already been made.
The Committee has directed that after obtaining the requisite information from the state government, the clearance(s) be issued by the Ministry of Environment and Forests within one month.
4. Pooling of price of imported coal with that of domestic coal
The Cabinet Committee on Economic Affairs had, in its meeting held on February 5 approved, in principle, broad guidelines and had directed that based on the guidelines, the Ministry of Coal should bring a proposal within five weeks.
Accordingly, the Committee, in its meeting held on April 22 considered the proposal of the Ministry of Coal and decided that the Coal India Limited will continue to supply domestic coal at 90 percent of the Annual Contracted Quantity (ACQ) for pre 2009 power projects. CIL will supply domestic coal at 65% of the ACQ to such post 2009 power projects that have been / will be commissioned by or before March 31, 2015 and where regular letters of Assurance have been issued and Power Purchase Agreements (PPAs) concluded on cost plus basis. This arrangement will not cover the projects where tapering linkages have been issued.
The Committee further decided that the details of other post 2009 power projects that have been/ will be commissioned by March 31, 2015 where (a) PPAs have been concluded on a competitive bid basis; (b) no PPAs have been signed; (c) projects with tapering linkages; and (d) projects with high bank exposure will be ascertained. The Committee directed that the detailed modalities in this regard be worked out within two weeks.
5. Fast Track Dispute Resolution Mechanism by National Highways Authority of India (NHAI)
Legal disputes and financial claims arise quite often in many highways contracts. Expeditious resolution of such disputes and settlement of claims are important from the point of view of timely implementation of the projects.
The Ministry of Road Transport and Highways apprised the Cabinet Committee on Economic Affairs of the new three-stage dispute resolution mechanism adopted by the NHAI. The old mechanism was not effective in expeditious resolution of disputes and claims. (ANI)